Meeting on: 25/11/2011 in Room 303C
Expected Attendees:
0901877
0907803
0907440
Agenda:
In the previous group meeting, we decided that it would be appropriate to reduce the number of group meetings in order to create focus on the actual project. If any group members have had any issues, then they have been relayed back to the team leader who has sorted them out accordingly. However, at the end of this week (Week 9) a group meeting has been arranged to discuss the following:
- How well the work is going so far.
- How much work is left to be done on the models so that we can begin the animation process.
- Do we need to make any adaptations to the Gantt chart created at the beginning of the project?
If any members have any issues, please do not hesitate to contact me.
Thanks.
Meeting on: 25/11/2011 in Room 303C
Attendees:
0901877
0907803
0907440
During the meeting, we agreed that although we will meet our target deadline, the other component to the module would suffer as a result so we all agreed that an extension would be the most appropriate course of action, seeing as this is our final year and every mark counts.
UPDATED: 02/12/2011
We have made adaptations to the Gantt chart and instead of having group meetings, we will meet up whenever we need help with aspects of the Guildhall and to put the whole project together. The image below shows the new Gantt chart which will be followed:
During the meeting, we agreed that although we will meet our target deadline, the other component to the module would suffer as a result so we all agreed that an extension would be the most appropriate course of action, seeing as this is our final year and every mark counts.
UPDATED: 02/12/2011
We have made adaptations to the Gantt chart and instead of having group meetings, we will meet up whenever we need help with aspects of the Guildhall and to put the whole project together. The image below shows the new Gantt chart which will be followed:
No comments:
Post a Comment